BUILDING PERMIT FEE SCHEDULE

All new buildings are subject to the following fees:

Please see below for more detailed fee information.

As per City of Fort Collins Code 7.5-16 & 7.5-19, permit fees are due at the time of permit issuance (not at time of application).
All fees are effective January 1, 2007

Building and Plan Review Fees:

Residential gas logs, wood stoves, air conditioning, furnace replacements, underground sprinklers, water heaters, and electrical service change are $15.00 plus City and County sales/use tax.

There is no plan check fee on sign permits (regardless of their valuation), and there is no plan check fee for valuations up to and including $3,000.

 

Building-Combination Estimate of Fees

Valuation: $

Bldg Permit Fee WO/Subs:

Permit Fees:
Plan Check Fee:
City Sales/Use Tax:
County Sales Tax:
Total:

Bldg Permit Fee W/Subs:

Permit Fees:
Plan Check Fee:
City Sales/Use Tax:
County Sales Tax:
Total:
 
Formula used for calculating Building Permit Fees ( as noted in the fee estimate calculator above )           Table 3A 1982 Uniform Building Code
Total Valuation Plan Review Building Permit Fee
$1.00 to $500.00 None $20.25
$501.00 to $2,000.00 None

$10.00 for the first $500.00 plus $1.50 for each additional $100.00 or fraction thereof to and including $2,000.00

Take this total times 1.35

$2,001.00 to $25,000.00

No plan review fee for valuations under $3,000.
Over $3,000 -- $32.50 for the first $2,000.00 plus $6.00 for each additional $1,000.00 fraction thereof to and including $25,000.00.

Take this total times .65

Use the formula in the column to the left, but take this total times 1.35

$25,001.00 to $50,000.00

$170.50 for the first $25,000.00 plus $4.50 for each additional $1000.00 or fraction thereof to and including $50,000.00.

Take this total times .65

Use the formula in the column to the left, but take this total times 1.35

$50,001.00 to $100,000.00

$283.00 for the first $50,000.00 plus $3.00 for each additional $1000.00 or fraction thereof to and including $100,000.00.

Take this total times .65

Use the formula in the column to the left, but take this total times 1.35

$100,001.00 to $10,000,000.00

$433.00 for the first $100,000.00 plus $2.50 for each additional $1000.00 or fraction thereof.

Take this total times .65

Use the formula in the column to the left, but take this total times 1.35

$10,000,001.00 and up

$25,183.00 for the first $10,000,000.00 plus $.10 for each additional $1000.00 or fraction thereof.

Take this total times .65

Use the formula in the column to the left, but take this total times 1.35